You are a project manager responsible for constructing a new sports arena in preparation for upcoming Olympics. Construction begins on a project over a year ago. Stakeholders of the project want a status report on the performance of the project to the date. You have obtained the following measurement:
BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=1.5 You believe the type of variances that have occurred on the project to date to be atypical, and except these variances to continue. Based on the information above what will be the VAC for the project?
A. 333.33
B. 133.33
C. 400
D. 166.67
E. 100