You have just completed the progress planning process group and are ready to begin the project executing process group. You will need to perform all the following executing processes except:

You have just completed the progress planning process group and are ready to begin the project executing process group. You will need to perform all the following executing processes except:
A. collect and distribute project performance information
B. improve competencies of team members
C. make necessary information available to stakeholder in time manner
D. obtain information , quotation and proposals
E. review offer and select seller