All of the following statements are true regarding the cost baseline EXCEPT:
A. The cost baseline is a part of the project management plan
B. The cost baseline is usually displayed as a S-shaped curve
C. Cost baseline is are management control point where budget and actual cost are integrated and compared to earned value for performance measurement
D. The cost baseline involves aggregating the estimating cost of individual activities or work packages and is an output of the cost budgeting process
E. A project may have multiple cost baseline