Which of the following statements are true?

You are the project manager at a software company developing the next-gen OODBMS (Object Oriented Data Base Management System). You are in the process of developing project schedule using CPM (Critical Path Method).
One of the disadvantages of CPM is that it does NOT consider resource availability. In fact, you’ve quickly identified that one of your key engineers, Michael, is over allocated. Which of the following statements are true?
A. You should use crashing in order to resource level the critical path tasks
B. You should use three point estimates in order to reassign the resource appropriately
C. You should use resource leveling heuristics to reassign the resource appropriately
D. You should fast track the process in order to resource level the critical path tasks.