Home » PMI » PMI-001 » Which of the following is the total amount of time that a scheduled activity may be delayed from its early start date without delaying the project finish date?
Which of the following is the total amount of time that a scheduled activity may be delayed from its early start date without delaying the project finish date?
A. Total float
B. Average float
C. None of the choices are correct
D. Critical float
E. Free float
Correct Answer: A
Explanation/Reference: