Which of the following statements are FALSE regarding project time management?

Which of the following statements are FALSE regarding project time management?
A. Schedule cost involving changes to the project schedule
B. Activity resource estimating involves estimating type and qualities of resources required to perform each schedule activity
C. None of the choices are correct
D. Activity sequencing involves identifying dependencies among schedule activities
E. Schedule development involves analyzing activity sequences, durations, resource requirements in order to create project schedule