Which of the following statements are true regarding the scope baseline for a project?

Which of the following statements are true regarding the scope baseline for a project?
A. The scope baseline is an output of the create WBS process.
B. The scope baseline is an output of the scope verification process
C. The scope baseline is an input of the create WBS process
D. The scope baseline is an input of the scope verification process
E. The scope baseline is an input of the scope control process