You are currently in process of prioritizing risks by their impact and probability of occurrence. The risk register updates from this process include all of the following EXCEPT:
Root cause of risks
A. Low priority risks
B. Risks group by categories
C. Risks requiring responses in the near term
D. Priority list of project risks