What is the minimum amount it will cost to save four months by crashing the project?

You are presented the following schedule data regarding various project activities on a critical path:


You are told that the project has negative float of 4 months. What is the minimum amount it will cost to save four months by crashing the project?
A. 10,000
B. 8,000
C. 7,000
D. 6,000
E. 9,000