You are in the process of monitoring the various project processes and their performance. Which of the following are you LEAST concerned with during this process?
A. Analyzing and tracking project risks
B. Monitoring the implementation of approved changes
C. Comparing actual project performance against project management plan
D. Providing forecast to update current schedule information
E. Assessing information to determine whether corrective actions are necessary
F. Reviewing and approving all recommended corrective and preventive actions