Which of the following best describes the amount of time one can delay the start of task without delaying the completion of the project?

Which of the following best describes the amount of time one can delay the start of task without delaying the completion of the project?
A. Lead time
B. Total slack
C. None of the choice are correct
D. Free slack
E. Lag time