Which of the following processes did you just complete?

You are the project manager for a software company that develops sports-based video games. You have been assigned to develop a new 3D interactive basket ball video game. You have just completed the development of the project scope management plan. Which of the following processes did you just complete?
A. Develop preliminary project scope statement
B. Cope definition
C. Scope control
D. Scope planning
E. Scope verification