Which of the following best describes the project integration Management Knowledge Area?

Which of the following best describes the project integration Management Knowledge Area?
A. Activity definition, activity sequencing, schedule control
B. Communications planning, information distribution, performance reporting, manage stakeholders
C. Develop project management plan, direct and manage project execution, integrated change control
D. Human resource planning, acquire project team, develop project team