You are using the three-point estimating technique to estimate the duration of a schedule activity. You are given the following data:
Pessimistic=200days
Optimistic=100days
Most likely=120 days
Average= 130 days
Variance= 277.7
Which of the following statements are true?
A. The calculations were performed assuming a UNIFOREM distribution
B. Not enough information is provided
C. The calculations were performed assuming a exponential distribution
D. The calculations were performed assuming a triangular distribution
E. The calculations were performed assuming a beta distribution