You are in the process of estimating the number of work periods that will be needed to complete individual schedule activities.

You are in the process of estimating the number of work periods that will be needed to complete individual schedule activities. All of the following are valuable inputs to this process except:
A. Schedule model data
B. Activity resource requirements, resource calendar
C. Duration estimating database
D. Historical information, historical reference data
E. Risk register, activity cost estimates