You are in the process of developing an approximation of the costs of the resources needed to complete each schedule activity.

You are in the process of developing an approximation of the costs of the resources needed to complete each schedule activity. All of the following are outputs of this process EXCEPT:
A. Cost management plan updates
B. Activity cost estimates
C. Activity cost estimate supporting detail
D. Requested changes
E. Cost baseline