Which of the statements regarding the WBS is FALSE?

Which of the statements regarding the WBS is FALSE?
A. A WBS from a previous project can often be used as a template for a new project
B. To identify the major deliverables of the project requires analyzing the detailed project scope statement
C. Different deliverables in the WBS can have different level of decomposition
D. The work activity is the lowest level of the WBS and is the point at which the cost and schedule for the work can be reliably estimated
E. The WBS is an output of the create WBS process