Which of the following are NOT inputs to this process?

You are in the process of identifying and documenting the logical relationships among schedule activities. Which of the following are NOT inputs to this process?
A. Project scope statement
B. Project schedule network diagram
C. Approved change requests
D. Activity lists, activity attributes
E. Milestones list