Which of the following is LEAST likely to improve the accuracy of cost estimates produced through parametric cost estimating technique?
A. When parameters used in the model are quantifiable
B. When model is scalable
C. When cost estimates of individual work packages are detailed and accurate
D. When historical information used to develop the model is accurate