Which of the following statement are correct regarding managing stakeholders except:
A. Managing stakeholders increases the likelihood that the project will not veer off track due to unresolved stakeholders issue
B. Tools used to manage stakeholders includes communication methods and issue logs
C. Project manager is usually responsible for stakeholder management
D. The manage stakeholder process is the part of project executing process group