Which of the following best describe how the project will be impacted?

One of your friends is project manager in Telecommunication Company. She is currently managing a project developing a voice over IP. The gateway offers a comprehensive approach to implementing high density, carrier class voice over packet gateway applications. She is in the process of developing the project schedule, and has determined that the project has 44 critical paths. Which of the following best describe how the project will be impacted?
A. Project will require more resources
B. There is no significant impact from having multiple critical paths
C. Project risk will increase
D. Project will cost more