You are in the process of directing the performance of the planned project activities and managing the various technical and organizational interfaces that exist within your project. All of the following are outputs of this process EXCEPT:

You are in the process of directing the performance of the planned project activities and managing the various technical and organizational interfaces that exist within your project. All of the following are outputs of this process EXCEPT:
A. Deliverables
B. Implemented WBS updates
C. Implemented defect repair, work performance information
D. Implemented corrective actions, implemented preventive actions
E. Requested changes, implemented change request