You are the project manager responsible for developing a new hybrid engine for a major auto manufacturer. You are in the process of developing the project schedule and would like to access the feasibility of your project schedule under various different conditions. Which of the following scheduling techniques is the LEAST appropriate?
A. Resource leveling
B. Schedule compression
C. Variance analysis
D. Monte Carlo analysis
E. Critical path method