Which of the following stages of Develop Project Team best describes your team?

You are the project manager for a manufacturer of children’s toys. Your project team is in process of designing a new children toy for next year’s Christmas season.
Your team meets and learns about the opportunity, agrees on goals and resources necessary to tackle the task. Although your team is highly motivated, they are relatively uninformed of the issues and objectives of the project. Which of the following stages of Develop Project Team best describes your team?
Performing
A. Forming
B. None of the choices are correct
C. Storming
D. Norming